Denimex Workover Solutions has completed workover of the DTEK Well # 43 Semyrenky with RDE-340K Snubbing Unit

Çîáðàæåííÿ
  • 07.08.2020 10:22:11

Denimex Workover Solutions has completed workover of the DTEK Well # 43 Semyrenky with RDE-340K Snubbing Unit

 Denimex Workover Solutions LLC has completed workover of the Well #43 of the Semyrenkivske Gas Field for PJSC Naftogazvydobuvannya (DTEK) without killing the well, using hydraulic snubbing unit. The operations in the well included POOH of production tubing, perforation job and RIH of the same tubing under pressure, allowing to increase the production of hydrocarbons.

The workover operations were performed with the Hi-tech 150-ton RDE-340K snubbing unit, one of the main advantages of which is the ability to work at the wellhead at a static pressure of over 5,000 PSI.
The application of snubbing technology allowed not to stop production from the well during the entire workover period. General workover time - 15.5 days.